PELLCO was the General Contractor for this project, which involved the installation of a new FieldTurf Synthetic Football Field, the construction of two grandstands totaling 3,000 seats and the construction of a new 2,000 sf masonry restroom/concession building. The project was on a 5 month construction schedule. PELLCO self-performed all earthwork, site utilities, structural concrete, rough carpentry and finish carpentry.


Value of Contract:

$2,844,103

Date of Completion:

September, 2005